Design of bulk sewer line, village reticulation and sewer treatment - Eastern villages (Phase 1)
Project Status:
Completed
Project Number: 823
Project Scope:

To design the bulk sewer line, village reticulation and sewer treatment plants.

In scope

  • Survey of bulk line route
  • Survey of village network
  • Survey of the sewer treatment plant location
  • Geotec survey
  • Design bulk serwer line
  • Design village reticulation
  • Design sewer treatment plant
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: Central Region, North East Region
Villages: Lesung, Marakana & Mosenthal, Serutube, Tantanana, Tlaseng, Tsitsing
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 26 March 2012
Baseline End Date: Friday 30 November 2012
Actual Start Date: Monday 26 March 2012
Actual End Date: Tuesday 11 December 2012
Schedule Variance:
-11 days
-4.418 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 