2024/16/07
Construction of TVET centre
Project Status:
Completed
Project Number: 870
Project Scope:

To construct a 1156 square meter building at the old post office for Royal Bafokeng Institute. The building will be used as the hospitality TVET facility.

In scope:

  • Construction of three classrooms and one staffroom;
  • Construction of a waiting areas;
  • Covered outdoor facility;
  • Construction of entrance canopy;
  • Construction of new entrance;
  • Construction of planter boxes;
  • Construction of pergola and storeroom;
  • Construction of new slab at Telkom;
  • Construction of Telkom ablutions;
  • Construction of external storm water structures;
  • Construction of internal and external paving;
  • Construction of screen wall; and 
  • Landscaping.
Key Focus Area: Public & Community Utilities
Focus Areas: Economic Development, Public & Community Utilities
Beneficiaries: Principals, Teachers, Community, Bafokeng SMME's
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 27 June 2012
Baseline End Date: Wednesday 5 December 2012
Actual Start Date: Wednesday 27 June 2012
Actual End Date: Wednesday 5 December 2012
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 3
Total: 3
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: