Upgrade and construction of new roads and parking areas in Diepkuil, Marakana (Mosenthal), Roodekraal and Thekwane.
Project Status:
Completed
Project Number: 920
Project Scope:

Construction and upgrade of 620 square meter turning area in Diepkuil, 0.222 Km internal road and 2958 square meter parking area in Kopman, 1.956 Km internal roads and storm water in Mosenthal, 2428 square meter turning area in Roodekraal and 1255 square meter parking area in Thekwane with 60mm interlocking block paving.

In scope:

  • Site establishment;
  • Clearing and earthworks-excavations and overhaul;
  • Prefabricated culverts and open drains;
  • Kerbing, channeling, chutes and concrete lining for open drains;
  • Pavement layers of gravel;
  • Concrete block paving for roads;
  • Ancillary works; and
  • Project completion handover.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: Central Region, North East Region, South East Region
Villages: Diepkuil (Maile), Kgale, Marakana & Mosenthal, Roodekraalspruit, Thekwane
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 28 July 2011
Baseline End Date: Monday 19 December 2011
Actual Start Date: Thursday 28 July 2011
Actual End Date: Friday 11 May 2012
Schedule Variance:
-144 days
-100 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 3
Total: 3