Road rehabilitation within the Bafokeng villages 2011
Project Status: |
Completed |
Project Number: |
931 |
Project Scope:
|
To rehabilitate paved and surfaced roads in the Bafokeng villages by 15 December 2011.
In scope:
- Installation of 1900m new pedestrian walkways in Robega and Thekwane;
- Repair edge breaks in Kanana, Thekwane, Tsitsing and Lefaragatlhe;
- Single seal to +/- 6 Km in Tsitsing and kanana roads;
- Slurry seal to +/- 9 Km from Tsitsing to Tantanana;
- Fox spary to +/15 Km Tsitsing Mogono-Sun City road and Thekwana - Mfidikwe road;
- Road markings Lesung - Marakana, Luka - Mogono, Kanana ring road, Mogono - Sun City road and other small areas;
- Re construction of several speed humps in Luka, Kanana and Serutube; and
- Reconstruction of 430m road between 430 Robega and Mafenya.
|
Key Focus Area: |
Public & Community Utilities |
Focus Areas: |
|
Beneficiaries: |
Community |
Regions: |
All Regions |
Villages: |
Chaneng, Kanana, Lefaragatlha, Lesung, Luka, Marakana & Mosenthal, Mfidikwe, Mogono, Thekwane, Tsitsing, All Villages |
Institutions: |
Infrastructure Maintenance |
Progress Actual: |
100 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Monday 29 August 2011 |
Baseline End Date: |
Thursday 15 December 2011 |
Actual Start Date: |
Monday 29 August 2011 |
Actual End Date: |
Friday 4 May 2012 |
Schedule Variance: |
-141 days -130.556 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden -244.103 %
|
Risks: |
0 |
Issues: |
Unresolved: 0 Resolved: 4 Total: 4
|
|
|