Road rehabilitation within the Bafokeng villages 2011
Project Status:
Completed
Project Number: 931
Project Scope:

To rehabilitate paved and surfaced roads in the Bafokeng villages by 15 December 2011.

In scope:

  • Installation of 1900m new pedestrian walkways in Robega and Thekwane;
  • Repair edge breaks in Kanana, Thekwane, Tsitsing and Lefaragatlhe;
  • Single seal to +/- 6 Km in Tsitsing and kanana roads;
  • Slurry seal to +/- 9 Km from Tsitsing to Tantanana;
  • Fox spary to +/15 Km Tsitsing Mogono-Sun City road and Thekwana - Mfidikwe road;
  • Road markings Lesung  - Marakana, Luka - Mogono, Kanana ring road, Mogono - Sun City road and other small areas;
  • Re construction of several speed humps in Luka, Kanana and Serutube; and
  • Reconstruction of 430m road between 430 Robega and Mafenya.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: Chaneng, Kanana, Lefaragatlha, Lesung, Luka, Marakana & Mosenthal, Mfidikwe, Mogono, Thekwane, Tsitsing, All Villages
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 29 August 2011
Baseline End Date: Thursday 15 December 2011
Actual Start Date: Monday 29 August 2011
Actual End Date: Friday 4 May 2012
Schedule Variance:
-141 days
-130.556 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
-244.103 %
Risks: 0
Issues: Unresolved: 0
Resolved: 4
Total: 4
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: