The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/16/07
Establishment of employee wellness programme (health)
Project Status:
Completed
Project Number: 968
Project Scope:

To help all employees with any physiological problems that  may hamper their perfomance through assessment and physical examination.

In scope

  • Advertise the project on Segoagoe, Dintshang and all staff
  • Develop a consultation template
  • Procurement of medical equipments
  • Implementation of the project
Key Focus Area: Health and Social Development
Focus Areas: Health and Social Development
Beneficiaries: RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 October 2011
Baseline End Date: Thursday 23 February 2012
Actual Start Date: Monday 3 October 2011
Actual End Date: Wednesday 16 May 2012
Schedule Variance:
-83 days
-58.042 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found