The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/16/07
Network infrastructure monitoring and management system
Project Status:
Completed
Project Number: 1076
Project Scope:

To install a network infrastructure monitoring and management system, that will monitor and perform preventative measures on the Royal Bafokeng Nation network infrastructure. The monitoring system will be installed internally, and all required material will be procured through the Auxiliary services department.

 In scope:

  • RBN network architectural review;
  • Network and topology documentation;
  • Acquisition of software;
  • Implementation;
  • Configuration; and
  • Monitoring.
Key Focus Area: Governance & Administration
Focus Areas:
Beneficiaries: Community, RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 5 November 2013
Baseline End Date: Thursday 5 December 2013
Actual Start Date: Tuesday 5 November 2013
Actual End Date: Tuesday 26 November 2013
Schedule Variance:
9 days
30 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0