Purchasing of additional earthworks plant and equipment
Project Status:
Completed
Project Number: 1115
Project Scope:

To purchase additional earthworks plant and equipment due to increased scope of work on implementation and maintenance of gravel roads in RBN villages.

In scope:

  • Procurement of 2x Motor graders;
  • Procurement of 2x 4*4 Tlb's;
  • Procurement of a 10 ton Vibro roller with canopy; and
  • Procurement of a 2x 14 000L sewer truck.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: All Regions
Villages: All Villages
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 7 February 2012
Baseline End Date: Friday 29 June 2012
Actual Start Date: Tuesday 7 February 2012
Actual End Date: Wednesday 22 August 2012
Schedule Variance:
-54 days
-37.762 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
22.388 %
Risks: 1
Issues: Unresolved: 0
Resolved: 1
Total: 1