Macharora schools sports facilities upgrade
Project Status:
Completed
Project Number: 1232
Project Scope:

To upgrade schools sports facilities by constructing mordern artificial turf soccer pitches and basketbal/netball courts in all five Macharora schools to improve the level of playing technique, skills and competency, to afford the good mordern playing surfaces and increase the property value of the schools.

In Scope:

  • Get a sponsor
  • Get a buy-in of the stakeholders
  • Appoint an acceredited and qualified contractor
  • Presentations to the SGB
  • Site inspection
  • Site clearance and occupation
  • Construction of the artificial turf pitches
  • Construction of basketball/netball courts
  • Site hand over
  • Close out report
Key Focus Area: Sport Development
Focus Areas: Education and Skills Development, Public & Community Utilities
Beneficiaries: Women, Youth
Regions: North Region
Villages: Chaneng, Mafenya, Rasimone, Robega
Institutions: Royal Bafokeng Sports (RBS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 22 February 2012
Baseline End Date: Friday 10 August 2012
Actual Start Date: Wednesday 22 February 2012
Actual End Date: Friday 10 August 2012
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

Gallery Images
Change rooms
Change rooms
Pitch
Pitch
Rasimone
Rasimone
Rasimone
Rasimone

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION