2024/17/07
Construction of sports facilities at Matale and Tumagole schools
Project Status:
Completed
Project Number: 1240
Project Scope:

To construct sports facilities comprising of two grass soccer fields and 2x basketball/netball courts at Matale and Tumagole schools.

In scope:

  • Setting out;
  • Excavation;
  • Compaction test;
  • G6 Layer;
  • Stabilisation;
  • Posts (Nom Sub- Contr);
  • Surfacing (Nom Sub-Contr);
  • Paving;
  • Gravel apron;
  • Line Markings; and 
  • Snag list.
Key Focus Area: Public & Community Utilities
Focus Areas: Sport Development
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 17 July 2012
Baseline End Date: Monday 10 September 2012
Actual Start Date: Tuesday 17 July 2012
Actual End Date: Thursday 10 January 2013
Schedule Variance:
-122 days
-221.818 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 0
Issues: Unresolved: 0
Resolved: 3
Total: 3