Archaeological Survey
Project Status:
Completed
Project Number: 1442
Project Scope:

To conduct archaeological survey of RBN land. The survey will cover all the five regions of the RBN and is intended to preserve the sites and the heritage associated with them for future generations and to document and map all archaeological sites discovered during the survey and make recommendations for rescue projects/any further archaeological work in the RBN.

In scope:

  • Do a preliminary visit of known RBN archaeological sites.
  • Identify sites to be covered in survey.
  • Draw terms of reference for consultant.
  • Procure a consultant to conduct survey.
  • Familiarize the consultant with RBN land (topography) through visits to known archaeological sites.
  • Conduct desktop study.
  • Conduct fieldwork-survey, documentation and mapping of discovered/known archaeological sites.
  • Draft report of the survey. 
  • Review report and submit comments to consultant.
  • Incorporate suggested/requested changes and finalise report.
  • Disseminate survey report to stakeholders and relevant research associates.

 

 

 

Key Focus Area: History and Heritage
Focus Areas: Education and Skills Development, History and Heritage, Governance & Administration
Beneficiaries: Principals, Teachers, Traditional leaders/Governance, Community, Bafokeng SMME's, RBN Employees, Senior Citizens, South African Government
Regions: North Region, Central Region, North East Region, South East Region, Capital Region
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Mabitse, Tlapa & Tlapa East, Tsitsing, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane
Institutions: Research
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 20 February 2013
Baseline End Date: Thursday 2 January 2014
Actual Start Date: Wednesday 20 February 2013
Actual End Date: Wednesday 8 January 2014
Schedule Variance:
-6 days
-1.899 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
7.014 %
Risks: 2
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 