The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/16/07
2013 Youth Election Conference
Project Status:
Completed
Project Number: 1524
Project Scope:

To facilitate a youth election conference which will be a platform to elect 14 new Bafokeng youth leaders that are going to be representative of 5 RBN Regions. The leadership will be a five year term contract. About 165 Youths from all 72 Makgotla will be invited to attend a 3 day conference which will be facilitated by an independent body. The conference will be run from 15-17 November 2013 at Rustenburg. Voting materials will be provided by the sponsors which will be identified. Facilitators and election observers will be selected among the youth invited to attend.

In scope:

  • Book venue that can accommodate 165 delegates for 2 nights and a big conferencing room to accommodate all delegates.
  • Approved service provider to cater for delegates.
  •  Inform all youth clubs about the conference
  • Identify the facilitator.
  • Identify and invite delegates.
  • Design the program.
  • Identify, design, procure and print complementary gifts.
  • Disseminate information about the youth conference to all makgotla.
  • Identify potential sponsors and seek sponsorship.
  • Close out report.
Key Focus Area: Health and Social Development
Focus Areas: Education and Skills Development, Economic Development, Governance & Administration
Beneficiaries: Youth
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 10 June 2013
Baseline End Date: Thursday 21 November 2013
Actual Start Date: Monday 10 June 2013
Actual End Date: Friday 28 February 2014
Schedule Variance:
-99 days
-60.366 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
-348.443 %
Risks: 4
Issues: Unresolved: 0
Resolved: 3
Total: 3
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION