Construction of new hostels at Lebone II college
Project Status:
Completed
Project Number: 1549
Project Scope:

To construct a 3 wing boarding house to accommodate 84 learners by the 27th of November 2013. The new hostels are being constructed to accommodate the increasing number of boarding students. Infraco will appoint qualified consultants to oversee and monitor the contractor that will be awarded the building tender.

In scope:

  • Construction of a bedroom space for 8 junior learners sharing with reasonable privacy screens (2 per wing);
  • Construction of a bedroom space for 4 learners sharing with reasonable privacy screens (2 per wing);
  • Construction of a bedroom/study for 2 senior learners (2 per wing);
  • Construction of a bedroom/study with small on suite ablution for a stooge (1 per wing);
  • Construction of homely ablutions (2 per wing one per floor);
  • Construction of an informal common space (2 per wing one per floor);
  • Construction of an entrance hall;
  • Construction of visitors ablutions;
  • Construction of an open plan dining room/study x 2;
  • Construction of  of an open plan kitchenette;
  • Construction of a games room (x2 one large one small);
  • Construction of a TV lounge x3;
  • Construction of an outdoor lounge (1 large and 2 small);
  • Construction of a cleaning store x3;
  • Construction of a drying yard x3;
  • Construction of a laundry collection booth x3; and 
  • Construction of a 2 bed junior staff apartment x4 with; open plan living, small kitchenette, separate entrance and direct entrance into boarding house, built in cupboards, main bedroom, bathroom with WC, WHB and shower, small second bed room, small veranda, small enclosed floor garden unit and a single covered parking close by.
Key Focus Area: Public & Community Utilities
Focus Areas: Education and Skills Development, Economic Development
Beneficiaries: Teachers, Children
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 21 May 2013
Baseline End Date: Wednesday 27 November 2013
Actual Start Date: Tuesday 21 May 2013
Actual End Date: Wednesday 10 September 2014
Schedule Variance:
-287 days
-151.053 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 4
Total: 4