Project Status: |
Completed |
Project Number: |
1252 |
Project Scope:
|
To produce a heritage route map in 2013 of the RBN by profiling all heritage and historical sites for preservation purposes.
The heritage map will come in two formats: the printable format and the online application format.
In scope:
- Research about sites
- Compilation of information about each site
- Seek technical assistance regarding production of map
- Consult with service provider for the online map application
|
Key Focus Area: |
History and Heritage |
Focus Areas: |
Environmental Management, History and Heritage, Governance & Administration |
Beneficiaries: |
Disabled, Local labourers, Principals, Teachers, Traditional leaders/Governance, Community, Bafokeng SMME's, Children, RBN Employees, Senior Citizens, Women, Youth, South African Government, Other Governments, Other Traditional authorities |
Regions: |
All Regions |
Villages: |
Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages |
Institutions: |
Research |
Progress Actual: |
100 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Thursday 2 May 2013 |
Baseline End Date: |
Monday 18 November 2013 |
Actual Start Date: |
Thursday 2 May 2013 |
Actual End Date: |
Thursday 10 July 2014 |
Schedule Variance: |
-234 days -117 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden 66.934 %
|
Risks: |
1 |
Issues: |
Unresolved: 0 Resolved: 1 Total: 1
|
|