The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/16/07
RBN Operations Room Phase 4.0
Project Status:
Completed
Project Number: 1255
Project Scope:

To further develop the OPMO system software in order to improve the user experience, increase or improve efficient and effective management of project and programmes and to address identified system needs in the RBN.

In scope:

  • Scoping of new features and developing mock-ups for each screen
  • Development of:
    • Inclusion of Tier 2 indicators
    • Changes to SKPI RAG measurement (Composite indicator)
    • First draft budget export option in the Treasury section
    • Service Delivery and Budget Implementation Plan (SDBIP)
    • Remove Strategic Key Focus Areas from the Strategy map
  • Manage the development of software solutions
  • Test new features
  • Roll-out of new features
Key Focus Area: Governance & Administration
Focus Areas: Economic Development
Beneficiaries: RBN Employees, Senior Citizens
Regions: Capital Region
Villages: Phokeng
Institutions: Organisational Performance & Project Management Office (OPMO)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 10 June 2013
Baseline End Date: Wednesday 14 August 2013
Actual Start Date: Monday 10 June 2013
Actual End Date: Tuesday 27 August 2013
Schedule Variance:
-13 days
-20 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 4
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION