2024/17/07
Project Status: |
Completed |
Project Number: |
1259 |
Project Scope:
|
To purchase five mobile classrooms for Matale and St. Gerald’s middle schools, to increase the number of classrooms to accommodate learners.
In scope:
- Procurement of five mobile classrooms; and
- Cast slab.
|
Key Focus Area: |
Public & Community Utilities |
Focus Areas: |
Education and Skills Development |
Beneficiaries: |
Principals, Teachers, Community, Bafokeng SMME's |
Regions: |
Capital Region, Central Region |
Villages: |
Kanana, Phokeng |
Institutions: |
Infrastructure Maintenance |
Progress Actual: |
100 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Tuesday 15 May 2012 |
Baseline End Date: |
Tuesday 11 September 2012 |
Actual Start Date: |
Tuesday 15 May 2012 |
Actual End Date: |
Wednesday 19 September 2012 |
Schedule Variance: |
-8 days -6.723 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden 76.312 %
|
Risks: |
1 |
Issues: |
Unresolved: 0 Resolved: 0 Total: 0
|
|
|
Milestones
Issues
Risks
Schedule
Milestones Calendar
Start Date: - End Date:
Tags:
|