2024/17/07
Renewable Energy- Solar Energy
Project Status:
Completed
Project Number: 1570
Project Scope:

To pilot a renewable solar energy project in the Bafokeng regions between RBED and Fraser Alexander. Project entails identification of local SMME to undergo technical training by the identified service provider from Fraser Alexander of solar energy installation. 50 homes in all Bafokeng region will benefit from the project as they will have the solar system installed in their houses. The project is scheduled to start in August 2013 and end March 2014.

In scope:

  • Identification of the SMME to be involved in the project/ Business
  • Identification of the sites (region, village, households) for conducting the pilot project
  • Identification and engagement of stakeholders- getting necessary permisions
  • Implementation/roll out of the project- installations
  • Skills training on renewable energy
  • Business management training
  • Feasibility study and a business plan
  • Facilitation of funds
  • Establishment of a business
  • Launching
Key Focus Area: Economic Development
Focus Areas: Education and Skills Development
Beneficiaries: Community, Bafokeng SMME's
Regions: North Region, Central Region, North East Region, South East Region, Capital Region
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 20 August 2013
Baseline End Date: Monday 28 July 2014
Actual Start Date: Tuesday 20 August 2013
Actual End Date: Friday 4 July 2014
Schedule Variance:
24 days
7.018 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 3
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

Gallery Images

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION