RBN Fixed Assets Verification
Project Status:
Completed
Project Number: 1576
Project Scope:

Following numerous audit queries from RBA External auditors regarding assets verification, RBA finance had to facilitate and ensure that it maintains accurate asset register to address and prevent future audit queries by appointing onsite and land auditors to conduct a fixed assets physical verification project from 27 May until 6 December 2013.

In Scope:

  • Appointing consulting company to conduct the project;
  • To have complete and accurate fixed asset register report from the appointed consultant;
  • Communicating project close out report to the COO.
Key Focus Area: Governance & Administration
Focus Areas:
Beneficiaries: RBN Employees
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Shared Services: Finance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 2 April 2013
Baseline End Date: Friday 6 December 2013
Actual Start Date: Tuesday 2 April 2013
Actual End Date: Wednesday 21 January 2015
Schedule Variance:
-411 days
-165.726 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
4.166 %
Risks: 3
Issues: Unresolved: 0
Resolved: 1
Total: 1