To install 12 boreholes and windmills to the identified Bafokeng grazing areas which have low water supply in order to assist our local farmers with water. The boreholes and windmills will be procured by RBN after a survey is done by the identified service provider to identify critical areas in the North and North East regions which have very low supply of water. The project will start the beginning of September and is planned to end in December 2013.
In scope:
Conduct water availability survey
Procurement processes
Identification of contractors
Contractors Implementation
Inspection and demonstration
Hand over
Key Focus Area:
Environmental Management
Focus Areas:
Economic Development, Food Security, Public & Community Utilities, Environmental Management