The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/16/07
RBED Business Portal (SMME database and Client Relationship Management system Phase 4)
Project Status:
Completed
Project Number: 1616
Project Scope:

To develop new functionality and build upon the SMME database and Client Relationship Management system software (RBED Business Portal) previously developed by conseptualising, scoping, developing and testing the newly developed functionality.  A software development company will be employed to do the actual development while the scoping and testing will be done in-house.  System go LIVE is expected for 30 November 2013.

In scope:

  • Development of new features:
    • Scoring of SMME  – An SMME evaluation tool to determine the business development stage of SMME, identify development needs and evaluate linkage readiness including associated reporting on the SMME loaded into the system.
    • Growth and other interventions – addition of system functionality to capture and manage worth and other interventions related to SMME development and expansion. This function includes the ability to develop standardized templates for ED interventions for existing SMME and capture the project plan as well as intervention progress or results.
    • Reporting  - reports on scoring results and SMME overview reporting providing a detailed interaction summary of RBED involvement are included in this scope.
  • System testing
  • Go live
Key Focus Area: Economic Development
Focus Areas: Economic Development, Governance & Administration
Beneficiaries: Community, Bafokeng SMME's, RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 2 September 2013
Baseline End Date: Tuesday 3 December 2013
Actual Start Date: Monday 2 September 2013
Actual End Date: Thursday 19 December 2013
Schedule Variance:
-16 days
-17.391 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0