RBN Operations Room Phase 5.0
Project Status:
Completed
Project Number: 1635
Project Scope:

To further develop the OPMO system software in order to improve the user experience, increase or improve efficient and effective management of project and programmes and to address identified system needs in the RBN.  The system development partner will be instructed to develop the new features in accordance to the specifications provided by the RBN OPMO.  The new features are expected to be live in August 2014.

In scope:

  • Scoping of new features and developing mock-ups for each screen
  • Development of:
    • Improvement in system speed - particularly the Work Breakdown structure
    • Development of the new online OPMO Monthly Report
    • Development of the new weekly email reports to executives
    • Install new Security License on the three related sites.
  • Manage the development of software solutions
  • Test new features
  • Roll-out of new features
Key Focus Area: Governance & Administration
Focus Areas: Economic Development
Beneficiaries: RBN Employees, Senior Citizens
Regions: Capital Region
Villages: Phokeng
Institutions: Organisational Performance & Project Management Office (OPMO)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 12 May 2014
Baseline End Date: Tuesday 29 July 2014
Actual Start Date: Monday 12 May 2014
Actual End Date: Monday 25 August 2014
Schedule Variance:
-27 days
-34.615 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 4
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found