2024/16/07
RBN Museum phase 1
Project Status:
Completed
Project Number: 1636
Project Scope:

To draft a detailed concept document, architectural plan and raise funds for the RBN museum that will be done in collaboration with the Rustenburg Local Municipality and the North West Dept of Sports, Arts & Culture. The museum will represent all the people of the Phokeng/Rustenburg area and will be built on Bafokeng land. It will be interactive and will reflect many different aspects of the region's history and present, including the cultures of the area, histories of migration, governance and socio-economic developments (such as land acquisition and mining), and future plans for the region. The first phase of the project will be completed by December 2016. 

In scope:

  • To establish a steering committee with all relevant stakeholders to conceptualize and plan the museum;
  • To consult the relevant RBN stakeholders and locate land for the museum;
  • To agree on the contents/themes of the museum and draft a concept document detailing these;
  • To draft terms of reference and appoint a service provider to draft architectural design and layout of the museum; and 
  • To raise funds for the actualization of the museum.
Key Focus Area: History and Heritage
Focus Areas: Economic Development, Governance & Administration
Beneficiaries: Teachers, Community, Children, Youth, South African Government, Other Traditional authorities
Regions: Capital Region
Villages: Phokeng
Institutions: Arts & Culture
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 12 January 2015
Baseline End Date: Thursday 3 September 2015
Actual Start Date: Monday 12 January 2015
Actual End Date: Friday 16 December 2016
Schedule Variance:
-470 days
-200.855 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
64.779 %
Risks: 4
Issues: Unresolved: 0
Resolved: 5
Total: 5
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found