Creation of cooperatives at regions
Project Status:
Completed
Project Number: 1695
Project Scope:

To facilitate the creation, formalisation, implementation, training and mentorship of 5 new cooperatives based in all Bafokeng regions. The aim is to develop the identified cooperatives and assist them in becoming self-sustainable. The project is set to be a fourteen month project. Kgwebo consultants has been appointed to be a service provider for the project and among other things they will do is to train the identified cooperatives. Selection for cooperatives will be done by the appointed service provider. The project will be implemented in 7 phases listed in the in scope.

In scope

Project phases

  • Selection process- facilitating 5 days’ workshop for selection process to
  • Identification of business opportunity for each cooperative (Facilitate women and youth into cooperatives)
  • Development of business plans and facilitation of funds through DTI incentive scheme, Identification and development of business model, grouping of management structures and cooperatives training, Development of business plans with financials project and facilitating DTI funding scheme.
  • Mentorship, implementation and setting up of business structure with all processes and management system
  • Business training and mentorship
  • Link to market and other business opportunities
  • Establish 5 new cooperatives.

Compiling and presentation of closeout report

Key Focus Area: Economic Development
Focus Areas: Economic Development
Beneficiaries: Bafokeng SMME's, Women, Youth, Other
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Royal Bafokeng Enterprise Development (RBED)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 February 2014
Baseline End Date: Monday 16 February 2015
Actual Start Date: Monday 3 February 2014
Actual End Date: Friday 10 July 2015
Schedule Variance:
-144 days
-38.095 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
51.381 %
Risks: 2
Issues: Unresolved: 0
Resolved: 3
Total: 3
Milestones

Issues

Risks

Schedule