Archaeological Sites Management Plan
Project Status:
Completed
Project Number: 1714
Project Scope:

To draft a comprehensive plan, by 30th November 2014, that will provide guiding principles for the use of the archaeological sites documented during the 2013 archaeological survey. The plan will be drafted by a service provider and will only be finalised after intensive stakeholder engagement.

The plan will ensure that the sites retain significance and are preserved if visited or developed for tourism purposes. It will also guide enhancement, presentation and maintenance of the sites.

The plan will provide guidance regarding the sites’ cultural significance, both provincially and nationally and is a statutory requirement for declaring sites as National/Provincial Heritage sites.

In scope:

  • Draft terms of reference for the consultant and procure services of consultant;
  • Hold inception meeting with consultant;
  • Review draft management plan;
  • Review final management plan;
  • Disseminate plan to relevant stakeholders; and
  • Draft action plan based on management plan.
Key Focus Area: History and Heritage
Focus Areas: Education and Skills Development, Economic Development, Environmental Management
Beneficiaries: Traditional leaders/Governance, Community, Bafokeng SMME's, South African Government
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Arts & Culture
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 7 April 2014
Baseline End Date: Friday 28 November 2014
Actual Start Date: Monday 7 April 2014
Actual End Date: Friday 30 October 2015
Schedule Variance:
-336 days
-142.979 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
4.175 %
Risks: 2
Issues: Unresolved: 0
Resolved: 4
Total: 4
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: