2024/16/07
Facilitate the establishment of Photsaneng Bakery
Project Status:
Completed
Project Number: 1721
Project Scope:

To coordinate the establishment of Photsaneng bakery at the identified centre, this will be revamped to meet the standards of a bakery. The bakery project was an idea of the identified local NGOs named ?Thari ya Thitelle?. The project is funded by RBH. This project is aimed at empowering local community members specifically women, creating jobs and alleviating poverty. Interested beneficiaries will be identified and screened to identify potential. There will be consultative meetings with traditional leadership in order to ensure that the project is known by Photsaneng residence. After the bakery is established the identified local NGO will ensure its management and sustainability. The project is planned to run from February to December 2014.

  • Identification of beneficiaries
  • Consultative meetings with traditional leadership
  • Identification of a service provider
  • Identification of a centre/ Venue
  • Facilitation of screening process to select people with relevant skills
  • Facilitation of training
  • Site visits with the service provider
  • Implementation of the project
Key Focus Area: Health and Social Development
Focus Areas: Education and Skills Development, Health and Social Development, Economic Development, Food Security
Beneficiaries: Community, Women, Youth
Regions: South East Region
Villages: Photsaneng
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 3 February 2014
Baseline End Date: Wednesday 1 April 2015
Actual Start Date: Monday 3 February 2014
Actual End Date: Wednesday 13 January 2016
Schedule Variance:
-287 days
-68.009 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 4
Issues: Unresolved: 0
Resolved: 3
Total: 3
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: