Project Status: |
Completed |
Project Number: |
1763 |
Project Scope:
|
To assist and advise the programming of HSDS and Protective Services, this desktop study will look at proven strategies and approaches for reducing alcohol abuse, particularly among youth. The desktop study is based on existing literature. The aim is to summarise best practices from other areas. Dr Arvin Bhana, a senior research on youth, substance abuse, health and wellbeing, will compile a report on these findings and best practices.
The desktop study is to include the following elements:
- Summary of current dominant thinking (globally and in South Africa) regarding effective strategies for reducing alcohol abuse, especially among youth (eg demand vs supply side management, awareness raising vs punitive measures, reduction of alcohol availability vs provision of alternative spaces and social activities, etc);
- Assessment of empirical evidence on effectiveness of different strategies, where available;
- Mapping of actors in the South and Southern African context with expertise and strong track records in facilitating reduction in alcohol abuse;
- Assessment of the applicability of different strategies to the Bafokeng context, given input from RBA key informants regarding existing knowledge and programming relating to alcohol abuse in the area;
- Provision of concrete policy recommendations and intervention options for consideration by RBA actors.
|
Key Focus Area: |
Health and Social Development |
Focus Areas: |
Safety and Security |
Beneficiaries: |
Community, Children, Women, Youth |
Regions: |
All Regions |
Villages: |
Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages |
Institutions: |
Research |
Progress Actual: |
100 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Monday 20 January 2014 |
Baseline End Date: |
Wednesday 15 October 2014 |
Actual Start Date: |
Monday 20 January 2014 |
Actual End Date: |
Wednesday 12 November 2014 |
Schedule Variance: |
-28 days -10.448 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden -1.212 %
|
Risks: |
2 |
Issues: |
Unresolved: 0 Resolved: 1 Total: 1
|
|