To facilitate the process of proposing new cemeteries for Royal Bafokeng Nation in all the regions. The process will be implemented by having consultative meetings with Makgotlas in every village and suggest possible areas for new cemeteries within their regions. Supreme Council will also be consulted regarding this matter to give approval. The project is planned to start in October 2013 and complete in December 2014. Once an agreement is reached, a consultant will be appointed to do Environmental Impact Assessment for all proposed cemetery sites as a separate project.
In scope:
Consultative meeting with Supreme Council
Consultative meetings with different Makgotlas
Feedback and approval from Dikgosana
Appointment of an EIA consultant.
Out of Scope:
Environmental Impact assessment
Key Focus Area:
Environmental Management
Focus Areas:
Health and Social Development, Public & Community Utilities, Environmental Management, Governance & Administration