2024/16/07
Construction of a new pipe line for section 1 and 2 of Madubu
Project Status:
Completed
Project Number: 1826
Project Scope:

To install water a water pipe line for section one and two of Madubu by the end of November 2014. The existing pipe needs to be replaced, the pipe has aged and as a result it has a lot of breakages.

The project will be implemented in the following manner:

Contractors – Local contractors that are used for general plumbing maintenance around the RBN villages to install the pipe.

Engineering consultants – To manage and monitor the project.

In scope:

  • Excavations;
  • Instillation of pipe;
  • Blanketing and backfilling; and
  • Construction of man hole.
Key Focus Area: Public & Community Utilities
Focus Areas: Economic Development
Beneficiaries: Community, Bafokeng SMME's, Women, Youth
Regions: Capital Region
Villages: Phokeng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Friday 29 August 2014
Baseline End Date: Friday 28 November 2014
Actual Start Date: Friday 29 August 2014
Actual End Date: Thursday 16 April 2015
Schedule Variance:
-139 days
-152.747 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: