2024/16/07
Rasimone bulk water supply
Project Status:
Completed
Project Number: 1831
Project Scope:

The construction of a bulk supply pipeline from the Nyee reservoir to the village of Rasimone. The pipe to be installed is a 315mm uPVC pipe which reduces to a 250mm within the village. Rasimone village is higher than other RBN villages; as a result the village experiences a lot of water shortages, by making this connection will improve the water supply to the area. The project will be done in conjunction with Royal Bafokeng Platinum, Anglo Glencore and Royal Bafokeng. The project will be overseen by a consultant, while a local contractor undertakes the construction; Royal Bafokeng Administration will only provide project management only. The project will be concluded by the end of January 2015.

In scope:

  • Contract administration and inspection;
  • Construction of pipeline; and 
  • Close-out.
Key Focus Area: Public & Community Utilities
Focus Areas: Economic Development
Beneficiaries: Local labourers, Community, Bafokeng SMME's, Children, Women, Youth
Regions: North Region
Villages: Rasimone
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 18 August 2014
Baseline End Date: Friday 16 January 2015
Actual Start Date: Monday 18 August 2014
Actual End Date: Monday 20 April 2015
Schedule Variance:
-94 days
-62.252 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: