2024/17/07
Community Perception and Feedback Reference Groups
Project Status:
Completed
Project Number: 1842
Project Scope:

To determine the level of RBN community satisfaction with services rendered by RBN entities and departments. This project will set up a community reference groups with 300 individuals, spreaod over various focus area and some sub-areas (governance, education, economic development, safety and security, health, etc.). The group will be a randomly selected statistically representative sample of the overall RBN population. These individuals will go through a very basic telephonic intake interview and then asked to make themselves available to answer questions (potentially by SMS) on issues relating to the focus area. Those who respond to the question will possibly receive free airtime as compensation. Most questions will be multiple choice and will relate to either personal experience (have you been a victim of crime in the past 6 months) or personal perception (do you think that overall safety in your village has a) increased, b) remained the same, c) decreased in the past three months).The research will be done in all regions and is planned to be completed in December 2015,  however, if sufficiently successful, we will motivate to repeat this over time.

In scope:

  • Appointment of the consultant;
  • Identify community reference groups with 300 individuals in each group for each strategic key focus area and some sub-areas;
  • Identify and appoint field workers;
  • Set up the Questionnaire;
  • Approval from different departments;
  • Discuss the questionnaire with the consultant;
  • Schedule;
  • Research; and 
  • Data analysis.
Key Focus Area: Governance & Administration
Focus Areas: All, Economic Development
Beneficiaries: Traditional leaders/Governance, Community, RBN Employees
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Research
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 17 June 2015
Baseline End Date: Friday 11 December 2015
Actual Start Date: Wednesday 17 June 2015
Actual End Date: Friday 12 February 2016
Schedule Variance:
-63 days
-35.593 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION