2024/16/07
Legato fiber installation
Project Status:
Completed
Project Number: 1853
Project Scope:

To install new fiber cables at legato, with proper conduit pipes. ICT recently discovered that the pipes used for old fiber from Legato Offices to Transport department were blocked and damaged by sand and roots and thus had to be redone. Trenching of conduit pipes from Legato offices to Royal house must be performed, including the upgrading of trenching to transport department. This will be done by a service provider under the supervision of ICT. The project will be completed by the end of November 2014.

In scope:

  • Survey site;
  • Trenching;
  • Installation and termination of fiber; and 
  • Configuration on switches.
Key Focus Area: Governance & Administration
Focus Areas:
Beneficiaries: Local labourers, Bafokeng SMME's, RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 15 September 2014
Baseline End Date: Monday 24 November 2014
Actual Start Date: Monday 15 September 2014
Actual End Date: Friday 28 November 2014
Schedule Variance:
-4 days
-5.714 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found