2024/17/07
Makgotla Communication Platform
Project Status:
Completed
Project Number: 1913
Project Scope:

To improve communication between Makgotla and the RBN`s central governance structures and therefore the entire administration and to streamline and standardize Makgotla processes. This project will commission the development of an application designed specifically to link Makgotla with central governance office. Each Kgotla will be issued with a tablet loaded with this application. The application will allow central governance to send information to Makgotla and Makgotla to send information to central governance in real time, including submitting Kgotla decision/voting, answering questions posed by central governance, and reporting attendance with photographs.

In scope

  • Makgotla needs scoped
  • Collection of data capturing books
  • Outsourced application development
  • Appointment of a designer 
  • Procurement of tablets and loading of the software
  • Capacity building for Dikgosana, Makgotla secretaries and central governance office
  • System test to end year
  • System test to end year

Scope Change Reguest:

Description: To exclude the procurement of tablets and installing the new application in them. It has been decided to use the manual system instead of the electonic system.

Key Focus Area: Governance & Administration
Focus Areas: Education and Skills Development, Economic Development, Governance & Administration
Beneficiaries: Traditional leaders/Governance, Community
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Secretary of Traditional Governance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 14 January 2015
Baseline End Date: Tuesday 22 December 2015
Actual Start Date: Wednesday 14 January 2015
Actual End Date: Tuesday 22 December 2015
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 1
Total: 1
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date: