Project Status: |
Completed |
Project Number: |
1939 |
Project Scope:
|
Royal Bafokeng Holdings commissioned a company called Trialogue to profile social project and Entreprise development project on the RBN. the aim of the study is to showcase these projects and the support RBN entities be it financial or training has provided. It will also serve as a lessons learned where the project managers will give advice on what works and what needs to be improved. This project aims to encourage the organisation to continue providing the best for morafe and to be reminded that the organisation is community satisfaction based. The RKM staff will go out with the fieldworkers and interview selected projects and take pictures of the outcomes. A one pager profile of the project will be developed.
In scope
- Invite an advisory team
- Set appointments with the projects
- Inception with Trialogue
- Field interviews
- Photographer
- Project profile
- Final profiles
|
Key Focus Area: |
Governance & Administration |
Focus Areas: |
Education and Skills Development, Health and Social Development, Economic Development, Food Security, Safety and Security, Public & Community Utilities, Environmental Management, Sport Development, History and Heritage, Governance & Administration |
Beneficiaries: |
Disabled, Local labourers, Principals, Teachers, Traditional leaders/Governance, Community, Bafokeng SMME's, Children, RBN Employees, Senior Citizens, Women, Youth |
Regions: |
All Regions |
Villages: |
Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages |
Institutions: |
Research |
Progress Actual: |
100 % |
Progress Planned: |
100 % |
Baseline Start Date: |
Wednesday 4 February 2015 |
Baseline End Date: |
Monday 1 June 2015 |
Actual Start Date: |
Wednesday 4 February 2015 |
Actual End Date: |
Monday 24 August 2015 |
Schedule Variance: |
-84 days -71.795 %
|
Approved Total Budget: |
Hidden |
Total Expenditures: |
Hidden |
Estimated to Complete: |
Hidden |
Total at Completion: |
Hidden |
Budget Variance: |
Hidden 100 %
|
Risks: |
3 |
Issues: |
Unresolved: 0 Resolved: 4 Total: 4
|
|