Installation of an Uninterrupted Power Supply (UPS)
Project Status:
Completed
Project Number: 1942
Project Scope:

To implement an uninterruptable power supply for Civic data center this will be feeding all four data rooms in the Civic center. The main purpose for implementing a UPS system is to ensure that unplanned power outages do not affect business operations, as it will allow the servers and switches to continue running during outages, and provides protection from power surges. The entire UPS system was procured in 2012; as a result the batteries have expired since they spent more than two years not operating. IT will have to procure new batteries and run with the installation thereafter. A service provider will be appointed to do the installation; the entire process should be done by the September 2015.

In scope:

  • Procurement of UPS batteries;
  • Appointment of service provider;
  • Installation of UPS;
  • Testing.
Key Focus Area: Governance & Administration
Focus Areas:
Beneficiaries: Traditional leaders/Governance, Community, Bafokeng SMME's
Regions: Capital Region
Villages: Phokeng
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Wednesday 1 July 2015
Baseline End Date: Friday 28 August 2015
Actual Start Date: Wednesday 1 July 2015
Actual End Date: Friday 28 August 2015
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 