NGO Profiling on Enterprise Development Module
Project Status:
Completed
Project Number: 2044
Project Scope:

To develop an NGO database within the Royal Bafokeng Enterprise Development (RBED) Module that will provide detailed information to funders/donors at the click of a button. This initiative was realised by the Strategic Relations Department as there was very little information on NGOs and the information that was available was somewhat disjointed.

It became necessary to centralise all information on NGOs that could accessible to funders/donors in order to secure funding that will enable NGOs to provide services to the community through various projects and programmes.

The project will be done in collaboration with the Health and Social Development Services Department and RBED. Information about the NGOs will be collected by HSDS, this information will be populated into the RBED ED Module and customized as per NGO requirements.

This project started in March 2013 and is envisaged to be up and running by end 2016.

In Scope:

  • Site visits and collection of NGO information;
  • Develop profiling data forms;
  • Monitor programme development;
  • Populate information onto the ED Module; and
  • Migration of information into customized NGO reports.

 

Key Focus Area: Health and Social Development
Focus Areas: Economic Development, Governance & Administration
Beneficiaries: Disabled, Community, Children, Senior Citizens, Women, Youth
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Strategic Relations
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Friday 1 February 2013
Baseline End Date: Wednesday 10 February 2016
Actual Start Date: Friday 1 February 2013
Actual End Date: Wednesday 1 June 2016
Schedule Variance:
-112 days
-10.145 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
100 %
Risks: 2
Issues: Unresolved: 0
Resolved: 2
Total: 2
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found