2024/16/07
Land use management workflow
Project Status:
Completed
Project Number: 1367
Project Scope:

To create a computer-based land-use management workflow for stand allocation applications, planning applications and development applications.

In scope:

  • Customize propriatary software for RBN needs;
  • Develop the work flow diagram according to the specific type of applications;
  • Capture data on the test environment;
  • Make ammendments where necessary; and
  • Go live/implement the system.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: RBN Employees
Regions: All Regions
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong, Luka, Chaneng, Diepkuil (Maile), Kanana, Serutube, Tantanana, Tlaseng, Marakana & Mosenthal, Roodekraalspruit, Kopman (Maile), Thekwane, Photsaneng, Mfidikwe, Mabitse, Tlapa & Tlapa East, Mogono, Tsitsing, Rasimone, Mafenya, Lesung, Mafika, Maile Extension, Leloreng, Motsitle (Mamerotse), Mogojane, Robega, All Villages
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 6 June 2011
Baseline End Date: Wednesday 17 October 2012
Actual Start Date: Monday 6 June 2011
Actual End Date: Friday 13 December 2013
Schedule Variance:
-422 days
-84.569 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 4
Total: 4