Monitoring Upgrading of Internal Roads in Robega Phase 3 - 2023
Project Status:
Completed
Project Number: 2664
Project Scope:

To undertake the construction of a 0.513km paved road, with 60mm interlocking paving, Fig 8b kerbs, and edge beams within Robega village, which is located in the North region. This project will be executed in collaboration with civil engineering consultants and the appointed contractor. The project timeline is expected to span from 3 October 2023, to 5 February 2023, with an estimated duration of four months.

RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion.

Project Milestones:

  • Site establishment;
  • Relocation and protection of existing services;
  • Conformance to road design layerworks;
  • Quality assurance by testing and approval of the road levels;
  • Paving and kerbing;
  • Road furniture; and 
  • Site handover. 
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Local labourers, Community, Bafokeng SMME's
Regions: North Region
Villages: Robega
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 3 October 2023
Baseline End Date: Monday 5 February 2024
Actual Start Date: Tuesday 3 October 2023
Actual End Date: Monday 5 February 2024
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 0
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 
All Rights Reserved | Copyright © 2024 - ROYAL BAFOKENG NATION