To undertake the construction of 1.518km road and stormwater v-drain and comprises of 80mm interlocking paving and three layer works at Chaneng located in the North region.
This project will be executed in collaboration with civil engineering consultants and the appointed contractor. The project timeline is expected to span from 11 April 2023 to 31 October 2023, with an estimated duration of six months.
RBN Infraco department will monitor the project through means of receiving and analysing progress reports and attending site meetings throughout the duration of the project that will come to conclusion.
Project Milestones:
Site establishment;
Relocation and protection of existing services;
Conformance to road design layerworks;
Quality assurance by testing and approval of the road levels;