2024/16/07
Lebone Server Room - Cabling Remediation
Project Status:
Completed
Project Number: 1385
Project Scope:

Lebone Server room changes to be completed by mid January 2013

In Scope:

  • Racks need to be moved to enable floor tiles to be cut and replaced, existing electrical connections must be remediated and new ones installed. Vermin control measures to be upgraded. 

  • The reason for this project is to enable future expansion in Lebone II server room, enhance existing processes & ensure safe operation with no unexpected down times due to electrical or structural failures.

  • Electrician and IT staff will be required  to co-ordinate operations for the duration of one day, minimising the downtime impact on RBN.

Key Focus Area: Governance & Administration
Focus Areas: Other
Beneficiaries: Principals, Teachers, Children, RBN Employees
Regions: Capital Region
Villages: Phokeng
Institutions: Shared Services: IT
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 4 October 2012
Baseline End Date: Thursday 13 December 2012
Actual Start Date: Thursday 4 October 2012
Actual End Date: Thursday 13 December 2012
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 4
Issues: Unresolved: 0
Resolved: 0
Total: 0