Project Status:
Completed
Project Number: 619
Project Scope:

To supply bulk electricity infrastructure to Lemenong, Tlaseng, Rathibedi TAU and Rathibedi stands the RBN villages.

In scope:

  • Survey of route design;
  • Site establishment;
  • Pole hole excavations;
  • Dressing an planting of holes;
  • Stringing of conductor;
  • Installation of airdac and service poles;
  • Installation of meters;
  • Handover to Eskom
  • Live line request; and 
  • Commissioning.
Key Focus Area: Public & Community Utilities
Focus Areas: Economic Development
Beneficiaries: Community
Regions: North East Region, North Region
Villages: Luka, Tlaseng
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Tuesday 1 May 2012
Baseline End Date: Wednesday 28 November 2012
Actual Start Date: Tuesday 1 May 2012
Actual End Date: Tuesday 29 January 2013
Schedule Variance:
-62 days
-29.384 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
0 %
Risks: 1
Issues: Unresolved: 0
Resolved: 1