The Royal Bafokeng Nation
The Royal Bafokeng Nation About the Royal Bafokeng How do we compare Publications Events Calendar Image Gallery Video Gallery Contact Us
 
 
 
 
 
2024/17/07
Infrastructure master plan for roads and storm water
Created Last modified Tuesday 16 July 2024 18:01 PM<< Back
Project Status:
Completed
Project Number: 638
Project Scope:

To develop a Phokeng Storm water drainage plan and Preliminary design. To enable the planning of the storm water system and to design solutions to resolve the storm water problems

In Scope:

  • Planning phase; and
  • Preliminary design phase.
Key Focus Area: Public & Community Utilities
Focus Areas:
Beneficiaries: Community
Regions: Capital Region
Villages: Phokeng, Kgale, Lefaragatlha, Bobounja, Lenatong
Institutions: Infrastructure Maintenance
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Monday 1 October 2012
Baseline End Date: Wednesday 19 December 2012
Actual Start Date: Monday 1 October 2012
Actual End Date: Wednesday 19 December 2012
Schedule Variance:
0 days
0 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
17.839 %
Risks: 2
Issues: Unresolved: 0
Resolved: 0
Total: 0
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Rated: No Votes
Tags:
 