2024/16/07
Debriefing of staff project (Phase 1)
Project Status:
Completed
Project Number: 678
Project Scope:

To reduce any possibility of psychological harm on HSDS employees who work under stressfull or traumatic enviroment  on a regular basis

In scope:

  • Identify members who need debriefing
  • Meetings
  • Identify  and contract service provider
  • Logistic arrangements
  • Facilitate the process of conducting debriefing sessions

 

Key Focus Area: Health and Social Development
Focus Areas: Education and Skills Development, Health and Social Development, Other
Beneficiaries: RBN Employees
Regions:
Villages:
Institutions: Health & Social Development Services (HSDS)
Progress Actual: 100 %
Progress Planned: 100 %
Baseline Start Date: Thursday 1 March 2012
Baseline End Date: Wednesday 16 May 2012
Actual Start Date: Thursday 1 March 2012
Actual End Date: Wednesday 4 July 2012
Schedule Variance:
-49 days
-64.474 %
Approved Total Budget: Hidden
Total Expenditures: Hidden
Estimated to Complete: Hidden
Total at Completion: Hidden
Budget Variance:
Hidden
98.442 %
Risks: 1
Issues: Unresolved: 0
Resolved: 5
Total: 5
Milestones

Issues

Risks

Schedule

Milestones Calendar
Start Date: - End Date:

No files found

Tags:
 