Projects |
To oversee the Environmental Impact Assessment (EIA) for the Mining
Right Application, Waste Management License and Water Use License. A
service provider is appointed to conducted an independent
environmental assessment and associated specialist s...
Project Status: Approved Active
Open Issues: 0
Duration: 1695 days
Project Manager: Reotshepile Tlhapane
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 72.3 %
|
|
Upgrading of CCTV and access control at the Civic Centre, Marang
Hotel and Plant Yard to address the shortcomings of the existing
systems and update capabilities to allow for future expansion and
enhanced security. The project is expected to run f...
Project Status: Approved Active
Open Issues: 1
Duration: 1090 days
Project Manager: Sonia Morele
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 97.7 %
|
|
To facilitate the process of procuring drone in order to enhace
Security services in RBN. The aim The aim of the project is to
establish the drone technology to conduct monitoring patrol in RBN
Land and Properties that will also provide support of...
Project Status: Approved Active
Open Issues: 0
Duration: 289 days
Project Manager: Sonia Morele
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 90.9 %
|
|
To facilitate the process of assets registration in e Royal Bafokeng
Nation's (RBN) This is to ensure that all the assets are registered in
the database and secured. This will be done through consultations with
RBN entities/departments based in Ph...
Project Status: Approved Active
Open Issues: 1
Duration: 214 days
Project Manager: Levy Nameng
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 37 %
|
|
To establish an industrial laundry facility that can effectively and
efficiently process clinic linen to ensure a continuous supply of
clean linen for healthcare users at the Bafokeng Health Centre. The
project will start on the 1st of May 2024 to...
Project Status: Approved Active
Open Issues: 1
Duration: 427 days
Project Manager: Millicent Mokgethi
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 6.9 %
|
|
To meet and listen to what PWD concerns are, what is it they really
need and to go back to the drawing board as an office to reflect if we
are making an impact. The dialogues are about reflection and to raise
awareness in this information sharing ...
Project Status: Approved Active
Open Issues: 1
Duration: 368 days
Project Manager: Letlhogonolo Mokalane
|
Internal Risks: 2
External Risks: 1
Budget: Hidden
Percentage Progress: 70.1 %
|
|
To improve patient management and ensure that personnel are up to
date with Continuous Professional Development (CPD) requirements
through the provision of various training courses by the end of May
2024. It is ideal for all EMRS practitioners to ...
Project Status: Approved Active
Open Issues: 0
Duration: 236 days
Project Manager: Dikeledi Petlele
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 16.2 %
|
|
To establish a fitness workout area Bafokeng clinic in Phokeng to
promote healthy lifestyles among patients and employees, while
concurrently emphasizing the high quality of healthcare service
delivery provided. The project will start on the 2nd O...
Project Status: Approved Active
Open Issues: 0
Duration: 365 days
Project Manager: Millicent Mokgethi
|
Internal Risks: 2
External Risks: 0
Budget: Hidden
Percentage Progress: 7.4 %
|
|
To undertake the construction of a 4.551km asphalt road which
comprises of 4m wide stormwater channel, speed humps, road markings,
signage, relocation of fence and existing electrical poles, concrete
splash drains, side drains at Mafenya/Chaneng l...
Project Status: Approved Active
Open Issues: 1
Duration: 237 days
Project Manager: Clifford Mpofu
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 74.3 %
|
|
The Royal Bafokeng Institute (RBI) will be hosting the RBI Arts
Festival, a one-of-a-kind event aimed at providing a platform for high
school learners in all RBN regions, to showcase their talent and
creativity in various art forms and to ...
Project Status: Approved Active
Open Issues: 1
Duration: 334 days
Project Manager: Boitumelo Sefemo
|
Internal Risks: 3
External Risks: 0
Budget: Hidden
Percentage Progress: 34.2 %
|
|
To revamp five (5) existing Meals on wheels centres located in South
East, Central and North East regions, villages namely Potsaneng,
Kopman, Tlaseng, Lesung, Tantanana. According to the 2022 PULA Survey
30% of the population fall below the food p...
Project Status: Approved Active
Open Issues: 4
Duration: 90 days
Project Manager: Rammitlwa Refilwe
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 13.7 %
|
|
The project aims to establish a support service specifically for
children with disabilities in the Royal Bafokeng Nation (RBN). This
project's primary goal is to foster and promote inclusion within RBN's
disability programmes for children. The ini...
Project Status: Approved Active
Open Issues: 3
Duration: 150 days
Project Manager: Letlhogonolo Mokalane
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 4.3 %
|
|
To roll out the Employee Wellness Programme as part of the HR core
strategic objective. The programme will assist employees experiencing
potentially work hampering, personal problems such as work stress,
marital conflict, family problems, emotiona...
Project Status: Approved Active
Open Issues: 0
Duration: 74 days
Project Manager: Festina Lephogole
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 28.8 %
|
|
To refurbish the Mountain Song Main Building by appointing
contractors to carry out essential plumbing maintenance, general
building maintenance, and electrical maintenance to ensure the
building is safe, functional, and suitable for occupation by...
Project Status: Approved Active
Open Issues: 1
Duration: 122 days
Project Manager: Orapeleng Legari
|
Internal Risks: 1
External Risks: 2
Budget: Hidden
Percentage Progress: 67.8 %
|
|
The Royal Bafokeng Administration has appointed WCS for maintenance,
remedial and replacement works at the Royal Bafokeng Sports Palace
(RBSP) to ensure the structural integrity and safety of the stadium,
enhance its aesthetics, comply with mainte...
Open Issues: 0
Duration: 180 days
Project Manager: Pat King
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
How
What
Why
When
Who
Where
In Scope...
Open Issues: 0
Duration: 0 days
Project Manager: Samuel Mahlangu
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
The Project and programme management training was developed in 2010
and has been delivereed in the same manner since. The office has since
evolved, moving from simply monitoring project and programme
activities to aligning budget with planning, em...
Open Issues: 0
Duration: 175 days
Project Manager: Rorisang Mathuloe
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 12.8 %
|
|
The construction of Lebone II - College was concluded in July 2010.
The school has been operational for the past thirteen years. It is in
fairly good condition due to the ongoing maintenance and upkeep that
has been done over the years. However, t...
Open Issues: 0
Duration: 0 days
Project Manager: Mpho Shikwambana
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 0 %
|
|
The day's purpose is to honour Nelson Mandela's legacy and encourage
people to take action for 67 minutes to improve the world and create a
worldwide movement for good. The 67 minutes symbolically represents
the number of years the former presiden...
Open Issues: 0
Duration: 108 days
Project Manager: Rammitlwa Refilwe
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 0 %
|
|
To ensure RBN buildings are insurable and in good condition, and to
address queries from the building insurer, we will undertake a
coordinated effort through a multidisciplinary committee. The core
issues to be addressed include structural integri...
Open Issues: 0
Duration: -19821 days
Project Manager: Karabo Rapoo
|
Internal Risks: 2
External Risks: 1
Budget: Hidden
Percentage Progress: 0 %
|
|
|