Projects |
1.Selection of U/17 and U/19 Platinum Stars Football Club Teams
To selected football players who will be developed over a period of
minimum two (2) years to be able to play for Platinum Stars Football
Club. The U/17 and U/19 teams will feed Pla...
Project Status: Completed
Open Issues: 0
Duration: 39 days
Project Manager: Moss Ramatja
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
Foundation Phase
RBI embarked on a mission to provide Molteno Breakthrough-to-Literacy
workshop trainings, for Foundation Phase Educators of 29 Primary
Schools within the Bafokeng Community(RBN). The programme is designed
in order to develop le...
Project Status: Completed
Open Issues: 0
Duration: 282 days
Project Manager: Lebo Molotsi-Molate
|
Internal Risks: 2
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To purchase additional earthworks plant and equipment due to
increased scope of work on implementation and maintenance of gravel
roads in RBN villages.
In scope:
* Procurement of 2x Motor graders;
* Procurement of 2x 4*4 Tlb's;
* Procur...
Project Status: Completed
Open Issues: 0
Duration: 143 days
Project Manager: Walter Katane
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
Create three additional offices in an existing classroom for use by
RBI staff. The offices will be built in the classroom previousy known
as the Food technology room. Construction will done in Glass and
Aluminium to fit in with the existing archit...
Project Status: Completed
Open Issues: 0
Duration: 83 days
Project Manager: Sean Lindsay
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
Convert two adjacent offices in the main administration building into
a boardroom by removing the common wall....
Project Status: Completed
Open Issues: 0
Duration: 64 days
Project Manager: Sean Lindsay
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
Monitor the progress and quality of repairs and upgrades of Royal
bafokeng basketball courts....
Project Status: Completed
Open Issues: 0
Duration: 48 days
Project Manager: Tshepo Malatsi
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To identify, procure and install the Phokeng Health Centre
rehabilitation room with necessary equipment which will be utilised to
rehabilitate all different types of physical dissabilities excluding
the deafs.
In scope:
* Identification of ...
Project Status: Completed
Open Issues: 0
Duration: 113 days
Project Manager: Meisie Mabothe
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To upgrade schools sports facilities by constructing mordern
artificial turf soccer pitches and basketbal/netball courts in all
five Macharora schools to improve the level of playing technique,
skills and competency, to afford the good mordern pla...
Project Status: Completed
Open Issues: 0
Duration: 170 days
Project Manager: Tshepo Malatsi
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To implement the electronic patient information system in the 7 RBN
clinics. A fully electronic Health record with a Master Patient Index
IN SCOPE:
* Deployment of necessary hardware to all 7 clinics.
* Configuration of the hardware and s...
Project Status: Completed
Open Issues: 0
Duration: 243 days
Project Manager: Meisie Mabothe
|
Internal Risks: 1
External Risks: 3
Budget: Hidden
Percentage Progress: 100 %
|
|
To upgrade and implement IT services that will enhance security,
monitoring and management of IT service in the Royal Bafokeng Nation.
In Scope:
* Design;
* Implementation;
* Wi-Fi security upgrade;
* Policy based authentication;
*...
Project Status: Completed
Open Issues: 0
Duration: 46 days
Project Manager: Isaac Modikwe
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To reduce any possibility of psychological harm on HSDS employees
who work under stressfull or traumatic enviroment on a regular
basis
IN SCOPE:
* Identify members who need debriefing
* Meetings
* Identify and contract service pro...
Project Status: Completed
Open Issues: 0
Duration: 76 days
Project Manager: Kabaro Neswiswa
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
Additions and repairs/refurbishment to existing Korean structure for
the RBHSS disability employment centre.
In scope:
* Additions to existing structure;
* Repairs to existing structure; and
* Refurbishment of existing structure.
...
Project Status: Completed
Open Issues: 0
Duration: 119 days
Project Manager: Walter Katane
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To conduct minor renovations at the Kanana, Chaneng and Phokeng
health centre emergency medical rescue service satellite stations, by
installing car ports.
In Scope:
* Construction of car ports at Kanana and Chaneng;
* Construction of ca...
Project Status: Completed
Open Issues: 0
Duration: 127 days
Project Manager: Michel Kops
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To conduct a session that will enlighten/inform the Executive members
on the accomplishments and challenges the RBN experienced for the past
year. This exercise allows the members to ask questions to the HOD's
and will eliminate long queues of sam...
Project Status: Completed
Open Issues: 0
Duration: -15401 days
Project Manager: Tumagole Tumagole
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To train pastors on marriage counselling
IN SCOPE
* Identify candidates who need training
* Identify and contract service provider
* Logistic arrangements, venue, catering, transport e.t.c
* Facilitate the process of conducting traini...
Project Status: Completed
Open Issues: 0
Duration: 112 days
Project Manager: Kabaro Neswiswa
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To purchase an Intermediate life Support Ambulance to improve
response time and upgrade the standard to intermediate life support.
In scope:
* Identification of vehicle;
* Procurement of vehicle;
* Specifications for conversions;
* Co...
Project Status: Completed
Open Issues: 0
Duration: 83 days
Project Manager: Michel Kops
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To raise awareness about issues affecting the elderly, sucn as
senescene and elderly abuse. To also appreciate the contributions that
older people make to the society. The celebration will be in hosted in
Robega and it will be in October month. Th...
Project Status: Completed
Open Issues: 0
Duration: 228 days
Project Manager: Mamakie Mothiba
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To save costs and preserve water in communities. The existing meters
will be faced out and a prepaid token will be used to access water.
Presentations on the project will be conducted to Makgotla Executives
and inputs and comments will be received...
Project Status: Completed
Open Issues: 0
Duration: 32 days
Project Manager: Tumagole Tumagole
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To facilitate the process of appointing the most suitable contractor
for TVET hospitality School building upgrade in phokeng, by working
hand in hand with the appointed consultents who assist us with the
technical requirements as well with bill of...
Project Status: Completed
Open Issues: 0
Duration: 67 days
Project Manager: Sipho Mbongwe
|
Internal Risks: 0
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To design the bulk sewer line, village reticulation and sewer
treatment plants.
In scope
* Survey of bulk line route
* Survey of village network
* Survey of the sewer treatment plant location
* Geotec survey
* Design bulk serwer lin...
Project Status: Completed
Open Issues: 0
Duration: 249 days
Project Manager: Sandra Kekae
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
|