Projects |
To further develop the OPMO system software in order to improve the
user experience, increase or improve efficient and effective
management of project and programmes and to address identified system
needs in the RBN. The system development partner...
Project Status: Completed
Open Issues: 0
Duration: 78 days
Project Manager: Jean Slabbert
|
Internal Risks: 3
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To rehabilitate the Royal Bafokeng Nation reservoirs, located in
Tsitsing, Tlaseng, Marakana and Mabitse. In 2012 a reservoir cleaning
project was initiated, at the conclusion of the project, a
close-report was compiled by the service provider of ...
Project Status: Completed
Open Issues: 0
Duration: 121 days
Project Manager: Sandra Kekae
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To initiate and promote disability awareness in the Central region,
in collaboration with disability forum towards addressing concerns as
raised on mind disability & other related issues. The campaign
therefore seeks to make the community aware of...
Project Status: Completed
Open Issues: 0
Duration: 15 days
Project Manager: Damaria Masilo
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To convey awareness to the community and married couples on issues
affecting marriages today and foster an enviroment that equips,
strengthens and builds strong and functional marriages. This will be
accomplished by organising a marriage workshop ...
Project Status: Completed
Open Issues: 0
Duration: 19 days
Project Manager: Kabaro Neswiswa
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To convey awareness to the community and married couples on issues
affecting marriages today and foster an enviroment that equips,
strengthens and builds strong and functional marriages. This will be
accomplished by organising a marriage workshop ...
Project Status: Completed
Open Issues: 0
Duration: 33 days
Project Manager: Kabaro Neswiswa
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To develop an integrated regional Master plan for the greater
Rustenburg area, with specific reference to economic growth and
diversification, spatial re-alignment, infrastructural integration and
recommend game changing projects. This will be don...
Project Status: Completed
Open Issues: 0
Duration: 297 days
Project Manager: Mpho Modisakeng
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
The focused ED approach entails the selection of a number of high
growth potential SMME and providing customised development
interventions such as technical mentoring business mentoring and
coaching, Bankable business plan, facilitate access to fu...
Project Status: Completed
Open Issues: 0
Duration: 1278 days
Project Manager: Talent Muzambi
|
Internal Risks: 0
External Risks: 4
Budget: Hidden
Percentage Progress: 100 %
|
|
To develop new functionality and build upon the SMME database and
Client Relationship Management system software (RBED Business Portal)
previously developed by conseptualising, scoping, developing and
testing the newly developed functionality. A s...
Project Status: Completed
Open Issues: 0
Duration: 205 days
Project Manager: Ian Venter
|
Internal Risks: 2
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
Following the repositioning of RBN, RBED like other departments had
to adapt so that it maintain its service offering to SMMEs and
Entrepreneurs. Aligned to our mandate of being sole conduit of all
SMME related activities, it is RBED's role to go ...
Project Status: Completed
Open Issues: 0
Duration: 35 days
Project Manager: Motlapele Tumagole
|
Internal Risks: 0
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
To initiate and promote disability awareness in the North East
region, in collaboration with disability forum towards addressing
concerns as raised by the forum itself - on persons with disabilities.
The campaign therefore seeks to make the commun...
Project Status: Completed
Open Issues: 0
Duration: 22 days
Project Manager: Damaria Masilo
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To develop Mfidikwe primary school As-built floor plans, the plans
are needed for the extension of classrooms. These plans will be
developed by use of a computer aided design software. This project has
been requested by the Royal Bafokeng Institut...
Project Status: Completed
Open Issues: 0
Duration: 62 days
Project Manager: Sasanki Motsie
|
Internal Risks: 2
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To create an enabling environment to Bafokeng stock farmers by
erecting crush pens for livestock at their grazing areas. Many local
farmers struggle with accessibility to crush pens, thus this project
will largely benefit them. All 3 crush pens wi...
Project Status: Completed
Open Issues: 0
Duration: 74 days
Project Manager: Gillian Senne
|
Internal Risks: 1
External Risks: 1
Budget: Hidden
Percentage Progress: 100 %
|
|
The construction of a bulk supply pipeline from the Nyee reservoir to
the village of Rasimone. The pipe to be installed is a 315mm uPVC pipe
which reduces to a 250mm within the village. Rasimone village is
higher than other RBN villages; as a resu...
Project Status: Completed
Open Issues: 0
Duration: 151 days
Project Manager: Sandra Kekae
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
The Royal Bafokeng Nation is considering lodging an application in
terms of the recently promulgated Restitution of Land Rights Amendment
Act (2014). This project commissioned an experienced researcher, Prof
Andrew Manson, to compile a list of pot...
Project Status: Completed
Open Issues: 0
Duration: 39 days
Project Manager: Tara Polzer-Ngwato
|
Internal Risks: 1
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To initiate and promote disability awareness in the South East
region, in collaboration with disability forum towards addressing
concerns as rose by the forum itself - on persons with disabilities.
The campaign therefore seeks to make the communit...
Project Status: Completed
Open Issues: 0
Duration: 15 days
Project Manager: Damaria Masilo
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To install water a water pipe line for section one and two of Madubu
by the end of November 2014. The existing pipe needs to be replaced,
the pipe has aged and as a result it has a lot of breakages.
The project will be implemented in the follow...
Project Status: Completed
Open Issues: 0
Duration: 91 days
Project Manager: Sandra Kekae
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
Based on inputs from a Committee of the Council of Dikgosana (RBN
traditional headsman) and historical documentation, the Research
Office has been mandated to draft a report compiling recent and
current practices relating to Bogosana Succession in...
Project Status: Completed
Open Issues: 0
Duration: 209 days
Project Manager: Tara Polzer-Ngwato
|
Internal Risks: 2
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To facilitate the process of procuring agricultural vehicles for RBA.
This is done to be able to assist all farmers within Bafokeng area,
especially crop farmers (Sunflower) so that they can produce a better
yield. Research will be made to determi...
Project Status: Completed
Open Issues: 0
Duration: 67 days
Project Manager: Tumisang Njikelane
|
Internal Risks: 0
External Risks: 2
Budget: Hidden
Percentage Progress: 100 %
|
|
To develop As-built plans for the Legato reception area, the plans
are needed for renovation purposes. The plans will be developed by use
of computer aided design software. This project has been requested by
the Office of Kgosi as it is a speciali...
Project Status: Completed
Open Issues: 0
Duration: 29 days
Project Manager: Sasanki Motsie
|
Internal Risks: 2
External Risks: 0
Budget: Hidden
Percentage Progress: 100 %
|
|
To implement a strategy to materially improve the quality of
education, and thus the prospects, for children in the current system
by establishing an _independent _school which will focus on Numeracy
and Literacy at the outset, for Grade 8s. This ...
Project Status: Completed
Open Issues: 0
Duration: 465 days
Project Manager: Ken Krige
|
Internal Risks: 0
External Risks: 3
Budget: Hidden
Percentage Progress: 100 %
|
|
|